May 7, 2026
Permit/Opening
1408 SONNY MILLER WAY BRUNSWICK, GA 31520
Inspection scores over time for this facility.
Georgia inspection history is score-based, with violations grouped under each recorded inspection.
Permit/Opening
Routine
Regulation: 511-3-5-.10(1)(a) - (a) pools shall use wall or floor inlets that are adequate in design, number and location to provide adequate mixing.
Observed return inlet covers missing at the time of this inspection. CA: Install inlet eyeball covers.
Permit/Opening
Regulation: 511-3-5-.10(1)(a) - (a) pools shall use wall or floor inlets that are adequate in design, number and location to provide adequate mixing.
Observed return inlet covers missing at the time of this inspection. CA: Install inlet eyeball covers.
Permit/Opening
Regulation: 511-3-5-.07(1)(e ) - (e) water clarity shall be maintained. when standing at the pool's edge at the deep end, the main drain suction outlet covers or a four inch by four inch square marker tile in contrasting color shall be clearly visible. when standing at a spa's e
Observed pool water unclear and unable to view the bottom of the pool at the time of this inspection. CA: Ensure pool is clear and bottom can be viewable without difficulty at all times.
Regulation: 511-3-5-.23(5)(a) - (a) during operation, disinfectant levels are less than the minimum level specified in dph rule 511-3-5-.17. if the level of the disinfectant used is not specified in dph rule 511-3-5-.17, the disinfectant must be approved and kept at levels determin
Observed chlorine levels less than 2ppm at the time of this inspection. CA: Increase chlorine level to 2-10ppm.
Regulation: 511-3-5-.17(2) - (2) chemical values: ph
Observed pH levels at 8.6 at the time of this inspection. CA: pH must remain at 7.2-7.8.
Permit/Opening
Regulation: 511-3-5-.23(5)(a) - (a) during operation, disinfectant levels are less than the minimum level specified in dph rule 511-3-5-.17. if the level of the disinfectant used is not specified in dph rule 511-3-5-.17, the disinfectant must be approved and kept at levels determin
Observed chlorine levels less than 2ppm at the time of this inspection. CA: Increase chlorine level to 2-10ppm.
Regulation: 511-3-5-.23(5)(c ) - (c) the pump, automatic disinfectant equipment, or other equipment necessary for continuous filtration and disinfection of the swimming pool, spa, or recreational water park attraction is not working or is unable to maintain adequate turnover rate.
Chemical feeder is believed to be clogged at not introducing chlorine into the pool at this time. CA: Repair feeder to properly introduce chlorine into the pool at all times.
Regulation: 511-3-5-.10(1)(c )1.ii. - (ii) the fitting shall not constitute a hazard to the user.
Observed return inlet covers missing at the time of this inspection. CA: Install inlet eyeball covers.
Routine
Routine
Regulation: 511-3-5-.23(5)(a) - (a) during operation, disinfectant levels are less than the minimum level specified in dph rule 511-3-5-.17. if the level of the disinfectant used is not specified in dph rule 511-3-5-.17, the disinfectant must be approved and kept at levels determin
Observed chlorine levels less than 2ppm at the time of this inspection. CA: Increase chlorine level to 2-10ppm.
Regulation: 511-3-5-.23(5)(c ) - (c) the pump, automatic disinfectant equipment, or other equipment necessary for continuous filtration and disinfection of the swimming pool, spa, or recreational water park attraction is not working or is unable to maintain adequate turnover rate.
Observed automated controller not operational at the time of this inspection. CA: Utilize alternative feeding method until repaired.
Permit/Opening
Routine
Regulation: 511-3-5-.06(1)(l) - (l) open joints or gaps larger than three-sixteenths inch wide or with vertical elevations exceeding 1/4 inches shall be rectified using appropriate fillers. construction joints where pool coping meets the decks shall be watertight and shall not allo
Observed facility with damage to the pool floor at the time of this inspection. CA: Facility will need to undergo resurfacing before opening for the 2024 Season.
Re-inspection
Regulation: 511-3-5-.06(1)(l) - (l) open joints or gaps larger than three-sixteenths inch wide or with vertical elevations exceeding 1/4 inches shall be rectified using appropriate fillers. construction joints where pool coping meets the decks shall be watertight and shall not allo
Observed facility with damage to the pool floor at the time of this inspection. CA: Facility will need to undergo resurfacing before opening for the 2024 Season.