Aug 19, 2025
Routine
31 HACKBERRY AVE COMMERCE, GA 30529
Inspection scores over time for this facility.
Georgia inspection history is score-based, with violations grouped under each recorded inspection.
Routine
Permit/Opening
Re-inspection
Regulation: 511-3-5-.07(1)(a) - (a) the equipment for a swimming pool shall be of adequate size to turn over the entire pool water capacity. the turnover rate for pools constructed after the adoption of this chapter shall not exceed the sum of one and one-half times the average wat
Unable to determine if pool is meeting required 6 hour turnover due to inoperable flow meter
Regulation: 511-3-5-.07(4)(b) - (b) a flow meter measuring the rate of flow through the filter system with an appropriate range readable in gallons per minute (gpm) and accurate within ten percent actual flow shall be provided. the flow indicator shall be capable of measuring from
Flow meter currently inoperable
Routine
Regulation: 511-3-5-.23(5)(a) - (a) during operation, disinfectant levels are less than the minimum level specified in dph rule 511-3-5-.17. if the level of the disinfectant used is not specified in dph rule 511-3-5-.17, the disinfectant must be approved and kept at levels determin
Chlorine below 1ppm
Regulation: 511-3-5-.23(5)(b) - (b) during operation, the ph is less than the minimum or more than the maximum levels allowed in dph rule 511-3-5-.l7.
pH below 7.2
Regulation: 511-3-5-.07(1)(a) - (a) the equipment for a swimming pool shall be of adequate size to turn over the entire pool water capacity. the turnover rate for pools constructed after the adoption of this chapter shall not exceed the sum of one and one-half times the average wat
Unable to determine flow due to inoperable flow meter
Regulation: 511-3-5-.07(4)(b) - (b) a flow meter measuring the rate of flow through the filter system with an appropriate range readable in gallons per minute (gpm) and accurate within ten percent actual flow shall be provided. the flow indicator shall be capable of measuring from
Flow meter currently inoperable
Permit/Opening
Routine
Regulation: 511-3-5-.23(3)(d) - (d) the operator shall receive a copy of the inspection and place it in a location protected from the weather and in public view as designated by the health authority.
Ensure inspection report is displayed in public view.
Permit/Opening