May 22, 2026
Re-inspection
506 REUNION CTR ATLANTA, GA 30331
Inspection scores over time for this facility.
Georgia inspection history is score-based, with violations grouped under each recorded inspection.
Re-inspection
Permit/Opening
Regulation: 511-3-5-.23(5)(b) - (b) during operation, the ph is less than the minimum or more than the maximum levels allowed in dph rule 511-3-5-.l7.
Observed pH level exceeding maximum.
Regulation: 511-3-5-.07(1)(a) - (a) the equipment for a swimming pool shall be of adequate size to turn over the entire pool water capacity. the turnover rate for pools constructed after the adoption of this chapter shall not exceed the sum of one and one-half times the average wat
Observed inadequate turnover rate per the flow meter reading for the 30k gallon pool.
Regulation: 511-3-5-.18(12)(c) - (c) the same sign in subsection (b) above or an additional sign will state under the heading “pool risks” the following items in clearly legible letters at least one inch high:
Observed failure to instal the ‘Pool Risks’ sign.
Re-inspection
Permit/Opening
Regulation: 511-3-5-.23(5)(b) - (b) during operation, the ph is less than the minimum or more than the maximum levels allowed in dph rule 511-3-5-.l7.
Observed pH level exceeding maximum. PH level shall be between 7.2-7.8. Advised management to adjust pH level.
Regulation: 511-3-5-.18(10)(b) - (b) a minimum one-fourth inch diameter throwing rope one and one-half times the maximum width of the pool or fifty feet in length, whichever is less, to which has been firmly attached a ring buoy with an outside diameter of approximately fifteen inch
Observed failure to make lifesaver readily deployable.
Observed inoperable water fountain at the pool deck area
Permit/Opening
Permit/Opening