May 27, 2026
Re-inspection
777 VALLEY BROOK CROSSING DECATUR, GA 30033
Inspection scores over time for this facility.
Georgia inspection history is score-based, with violations grouped under each recorded inspection.
Re-inspection
Permit/Opening
13-189(c): Water shall be of such clarity that main drains are visible. Observed minimal water clarity and was unable to visualize main drains.
13-188(f): All steps shall have ladders installed and secure. Observed loose grab/handrails of pool ladder. CPO corrected the issue on-site to properly secure rails.
Routine
One of the handrails was loose. I was able to dislodge it entirely
Permit/Opening
Routine
Current permit was not displayed
Routine
Permit/Opening
Routine
13-188(h)(4): decks shall not retain any standing water. There is standing water on the pool deck.
Routine
13-189(c)(1): the chlorine residual in all parts of the pools shall be maintained at a minimum of 3.0ppm-10.0ppm. The chlorine was at 1.96 and was COS to 5.02
Permit/Opening